RISK MITIGATION IN SUPPLY CHAIN DISRUPTION DURING PANDEMIC COVID-19 IN EPC PROJECT, STUDY CASE PT XYZ

Authors

  • Arpan Marwazi Lubis Program Studi Magister Administrasi Bisnis Fakultas Ilmu Sosial dan Ilmu Politik Universitas Katolik Parahyangan
  • Maria Widyarini Program Studi Magister Administrasi Bisnis Fakultas Ilmu Sosial dan Ilmu Politik Universitas Katolik Parahyangan
  • Oki Sunardi Program Studi Magister Administrasi Bisnis Fakultas Ilmu Sosial dan Ilmu Politik Universitas Katolik Parahyangan

Keywords:

COVID-19 Risk, Construction Safety, Mitigation Strategies, Supply Chain Management, Disruption

Abstract

The COVID-19 pandemic, which began in early 2019 and persists to this day in 2022, stands as one of the most significant global disasters in recent years. Beyond the staggering number of fatalities and hospitalizations, its impact encompasses widespread economic repercussions, extensive business interruptions, and significant hardships worldwide. Its spread has profoundly affected various sectors of the global economy, including manufacturing, hospitality and tourism, finance, food and beverage, as well as the construction industry in Indonesia. Numerous projects in Indonesia suffered delays and increased costs due to the pandemic. Construction activities abruptly ceased at various sites, leading to a stagnation in productivity. In light of these circumstances, this study focuses on the initial challenges encountered in managing the COVID-19 crisis and its specific implications on the construction sector. This study investigated the impact of the COVID-19 pandemic on EPC (Engineering, Procurement, and Construction) companies in Indonesia. The analysis was conducted based on feedback obtained from 11 respondents belonging to SCM (Supply Chain Management) Departments, comprising SCM managers and Logistics managers from major international EPC companies operating in oil, gas, power, petrochemicals, and related services engaged in ongoing EPC projects within Indonesia. These respondents shared insights derived from their experiences in addressing the disruptive effects of the pandemic. They highlighted the overall negative impacts encountered, newly emerged opportunities, and ongoing efforts in risk management. The reported adverse effects encompassed significant project delays, challenges in acquiring materials on time, reduced productivity rates, increased logistics expenses, escalations in material costs, shifts in transportation methods (from sea freight to air freight) to meet construction schedules, among other challenges. The Supply Chain disruption caused various impacts, particularly on material, finance, and information flows. Material movements and deliveries experienced significant delays due to disruptions. Finance flows, including payment terms for both sellers and buyers, were also affected, causing disruptions in transactions. Information flow across multiple aspects, including human resources, material stock information, quotations, inspections, Health, Safety, and Environment (HSE), and scheduling, faced challenges. Risk management strategies were significantly bolstered to address these issues, focusing on enhancing safety measures (HSE) and mitigating other project risks like delivery delays and handover issues. Safety measures were intensified, mandating employees to wear medical face masks, undergo body temperature checks below 37 degrees Celsius, adhere to social distancing protocols, implement staggered construction operations, provide COVID-19-related training, conduct temperature checks before entry to workplaces, frequently administer antigen tests/PCR tests, and other precautionary measures to ensure safety and minimize the risk of virus transmission.

Downloads

Download data is not yet available.

References

[FIDIC] International Federation of Consulting Engineers. 1999. Condition of Contract for EPC Turnkey Projects, Laussanne, Switzerland.

[PMI] Project Management Institute. 2004. ’ A Guide to Project Management Body of Knowledge’, fifth edition, Project Management Institute Inc.

Aigbavboa, C. O., Aghimien, D. O., Thwala, W. D., & Ngozwana, M. N. (2022). Unprepared industry meet pandemic: COVID-19 and the South Africa construction industry. Journal of Engineering, Design and Technology, 20(1), 183-200.

Bajomo, M., Ogbeyemi, A., & Zhang, W. (2022). A systems dynamics approach to the management of material procurement for Engineering, Procurement and Construction industry. International Journal of Production Economics, 244, 108390.

Behera, P., Mohanty, R., & Prakash, A. (2015). Understanding construction supply chain management. Production Planning & Control, 26(16), 1332-1350.

Cabano SL 2004, ’ Do we truly understand project risk?’, AACE International Transaction, pp. R131-36. Retrieved September 17, 2006.

Chandra C., Kumar S., Enterprise architectural framework for supply chain integration, Industrial management and data systems, 101/6, 2001.

Cohen M. A. and Lee H. W., Strategic Analysis of Integrated Production Distribution Systems: Models and Methods. Operations Research, Vol.36, No.2, March-April 1988.

Cohen MW and Palmer GR 2004, ’ Project risk identification and management’, AACE International Transaction, pp.13- 15. Retrieved September 10, 2006 from ABI/INFORM Glob

Cooper, D. F., Grey, S., Raymond, G., & Walker, P. (2005). Project risk management guidelines. Wiley.

Cooper, M. C., and Ellram, L. M., Characteristics of Supply Chain Management and the Implications for Purchasing and Logistics Strategy. Intl. J. Log. Mgmt., 4 (2), 1993.

Cooper, M. C., Lambert, D. M., and Pagh, J. D., Supply Chain Management: More Than Just a New Name for Logistics. Intl. J. of Logistics Mgmt., 8 (1), 1997.

Edward PJ and Bowen PA (1998), ’ Risk and risk management in construction : a review and future direction for research’, Engineering, Construction and Architectural Management, vol. 5, no. 4, pp. 339-349.

Han, E., Tan, M. M. J., Turk, E., Sridhar, D., Leung, G. M., Shibuya, K., Asgari, N., Oh, J., García-Basteiro, A. L., & Hanefeld, J. (2020). Lessons learnt from easing COVID-19 restrictions: an analysis of countries and regions in Asia Pacific and Europe. The Lancet, 396(10261), 1525-1534.

Hu, W., & He, X. (2014). An innovative time-cost-quality tradeoff modeling of building construction project based on resource allocation. The Scientific World Journal, 2014.

Jeon, J., Padhye, S., Bhattacharyya, A., Cai, H., & Hastak, M. (2022). Impact of COVID-19 on the US Construction Industry as Revealed in the Purdue Index for Construction. Journal of Management in Engineering, 38(1), 04021082.

Kartam, N. A., and Kartam, S. A. (2001). “Risk and its management in the Kuwaiti construction industry: a contractors’ perspective. ˮ International journal of project management, 19(6), 325-335.

Labombang, M. (2011). Manajemen risiko dalam proyek konstruksi. SMARTek, 9(1).

Poage WS 1990. ’ The Building Professional’s Guide to Contract Document’s’. North America (US): RS Means Company Inc.

Project Management Institute Standards Committee. (2004), A Guide to the project management body of knowledge, PMI

Sholeh, M. N. (2020). Manajemen Rantai Pasok Konstruksi. Pustaka Pranala.

Sholeh, M. N., & Fauziyah, S. (2018). Current state mapping of the supply chain in engineering procurement construction (EPC) project: a case study. MATEC Web of Conferences,

Sholeh, M. N., & Fauziyah, S. (2021). Pengadaan Material Proyek Engineering Procurement Construction. Pustaka Pranala.

Tang, T. (2015). “Research on the risk identification for the international engineering contracting epc projects. ˮ Proceedings of the 21st International Conference on Industrial Engineering and Engineering Management 2014 (pp. 477-482). Atlantis Press.

Wang SQ, Dulaimi MF and Aguira MY 2004. ’Risk management framework for construction projects in developing countries’, Construction Management and Economics, vol. 22, pp. 237-252.

Wang, S. Q., Dulaimi, M. F., and Aguria, M. Y. (2004). “Risk management framework for construction projects in developing countries. ˮ Construction Management and Economics, 22(3), 237-252.

Wang, T., Abdallah, M., Clevenger, C., & Monghasemi, S. (2021). Time–cost–quality trade-off analysis for planning construction projects. Engineering, Construction and Architectural Management, 28(1), 82-100.

Zhi H 1995. ’Risk management for overseas construction project’. International Journal of Project Management, vol. 13, no. 4, pp.231-237

Downloads

Published

2023-11-09

How to Cite

Arpan Marwazi Lubis, Maria Widyarini, & Oki Sunardi. (2023). RISK MITIGATION IN SUPPLY CHAIN DISRUPTION DURING PANDEMIC COVID-19 IN EPC PROJECT, STUDY CASE PT XYZ. Jurnal Ekonomi, 12(04), 1404–1416. Retrieved from https://ejournal.seaninstitute.or.id/index.php/Ekonomi/article/view/3183